Xinhua Net reports on the company’s ongoing construction of the Tuanhe Section of the South-to-North Water Diversion Project.
World’s Largest U-Shaped Aqueduct—First Span of the Tuanhe Aqueduct for the South-to-North Water Diversion Project Successfully Cast
BEIJING, Nov. 9 (Xinhua) — According to information obtained on November 9 by reporters from the Construction Administration of the Middle Route of the South-to-North Water Diversion Project from the project’s management bureau, the first span of the main structure of the Tanhe Aqueduct in Dengzhou, Henan Province—the world’s largest U-shaped water-conveyance aqueduct under the South-to-North Water Diversion Project—has successfully completed concrete pouring. With this milestone, the Tanhe Aqueduct project has now entered the main construction phase.
According to available information, each segment of the water-conveyance aqueduct consists of three U-shaped openings, with each opening forming a single truss. Following the official commencement of the Tuanhe Aqueduct Project on December 28, 2010, construction workers first undertook the installation of underground pile foundations. After 108 days of intensive work, they successfully completed the grouting of 342 friction piles, and on June 12 of this year, the project transitioned from underground operations to above-ground construction. On November 2,
The first span of the Tanhe Aqueduct has successfully completed concrete placement. Following a 7-day curing period, the internal formwork of the form-moving machine was smoothly removed, and on-site inspection confirmed that the concrete quality of the first aqueduct segment meets the design requirements.
Unlike precast trough sections, the Tanhe Aqueduct employs an on-site concrete placement technique using a trough-forming machine. This method not only mitigates the impact of topography and landforms on the construction site but also minimizes disruptions to construction scheduling during the flood season. Its structural design is innovative, and the construction processes and equipment employed are unprecedented; as such, it has been designated by the state as a key research project under the 12th Five-Year Plan for Technological Equipment and as a priority science-and-technology initiative of the State Council’s South-to-North Water Diversion Office.
The Tuanhe Aqueduct is a key control project on the central route of the South-to-North Water Diversion Project, ranking first in the world in terms of internal diameter, single-span length, and maximum water conveyance capacity. Located over the Tuanhe River between Zhangpo Village in Shilin Town and Jizhai Village in Zhaoji Town in Dengzhou City, Henan Province, the aqueduct has a total length of 1,030 meters. Its structure consists of 18 independent, prestressed concrete U-shaped channels, each with three separate compartments, with a single-span weight of up to 1,600 tons. Each compartment has an internal clear dimension of 7.23 × 9.0 meters, a design flow rate of 350 cubic meters per second, and a maximum flow rate of 420 cubic meters per second.
Note: The “currently largest U-shaped water-transfer aqueduct in the world” mentioned in this press release was constructed using the DZ40/1600U trenching machine designed and manufactured by Xinfangda Heavy Industry Technology Co., Ltd.
Xin Dafang has successfully won the bids for three major projects under the Middle Route of the South-to-North Water Diversion Project, setting three world-first records. These three projects are: the Shahe Project, featuring 1,200-ton lifting, transportation, and erection equipment; the Shuanglei River Project, with a 30-meter-span, 2,500-ton, two-span rectangular aqueduct-forming machine; and the Tuanhe Project, equipped with a 40-meter-span, 1,600-ton U-shaped aqueduct-forming machine.
Keywords:
Related blog
Address: No.1, Minghui Road,Mazhai Industrial Park, Erqi District, Zhengzhou, Henan Province
Tel: +86-371-60305013
Email: shenshangda@zzdf.cn baomin@zzdf.cn
What'sapp: 008615515866566
Facebook ID: Zhengzhou New Dafang
Copyright © Zhengzhou New Dafang Heavy Industry Science And Technology Co., Ltd.
Powered by :www.300.cn Supported IPV6 Privacy Agreement
COOKIES
Our website uses cookies and similar technologies to personalize the advertising shown to you and to help you get the best experience on our website. For more information, see our Privacy & Cookie Policy
COOKIES
Our website uses cookies and similar technologies to personalize the advertising shown to you and to help you get the best experience on our website. For more information, see our Privacy & Cookie Policy
These cookies are necessary for basic functions such as payment. Standard cookies cannot be turned off and do not store any of your information.
These cookies collect information, such as how many people are using our site or which pages are popular, to help us improve the customer experience. Turning these cookies off will mean we can't collect information to improve your experience.
These cookies enable the website to provide enhanced functionality and personalization. They may be set by us or by third-party providers whose services we have added to our pages. If you do not allow these cookies, some or all of these services may not function properly.
These cookies help us understand what you are interested in so that we can show you relevant advertising on other websites. Turning these cookies off will mean we are unable to show you any personalized advertising.