DP80/35 model section Segmental Bridge Erection Machine Complete Equipment Specifications
Clearance from the main girder to the erected girder deck: 4.0m
Span of the structure: 25m 、27 m 、30 m 、35 m
Feeding method: under the bridge or at the front end of the bridge-launching girder (not exceeding the bridge deck) 20m)
Operating Altitude less than or equal to 2000m
Operating ambient temperature (meteorological temperature): -20 degree C~+50 degree C
Overall machine longitudinal traverse hole-passing speed: 0–1 m/min
Lateral adjustment range of the entire girder: ±150 mm
Work efficiency: 3 days/cross (time consumed by bridge-launching girder erection)
Working environment wind speed: operating wind pressure ≤300N/m2
Non-operational wind pressure ≤ 800 N/m 2
Night-time construction lighting: meets the requirements of nighttime operations.
Total Power (External Power Supply Mode): 130kW