What inspections should be carried out during the load test of a girder transporter?


  In order to ensure Beam transporter To ensure safety and normal operation, newly installed equipment that is ready for commissioning must undergo a load test. Next, we will discuss the inspections that should be carried out during the load testing of girder transport vehicles.

  Pre-test examinations:

  1. Clean the entire machine thoroughly to remove all debris left on it during installation.

  2. Clean the test site and remove all residues unrelated to the test run.

  3. Verify that the assembly complies with the design requirements.

  4. Verify that the overall dimensions of the girder transporter comply with the design specifications; inspect the metal structure for deformation, check the tightness of all connections, examine the winding and tensioning of the wire ropes, and ensure that the buffer is aligned with the center of the impact head.

  5. The corresponding lifting attachments shall be fully equipped for the lifting test load.

  6. Inspect the installation quality of the mechanical components, including whether the transmission rotates smoothly, whether the oil pump and indicator in the lubrication system operate flexibly, and whether the oil lines are unobstructed.

  8. Inspect the clearance between the trolley wheels and the track, and remove any obstacles or unnecessary items that may interfere with the test.

  9. Corresponding tests shall also be conducted on electrical equipment.

  The foregoing outlines the inspection items that must be carried out prior to the load test of the girder transporter. We hope this information proves helpful.